Test Production Metrics: Cycle Time and Throughput Rate
Agenda
QUESTION 1: What does Cycle Time measure?
Meeting time
Time from the start to the end of a task
Break time
Planning time
2nd QUESTION: What does Throughput measure?
Items completed per period
Hours worked
Money earned
Estimated points
3rd QUESTION: What does Little's Law state?
WIP = Throughput / Cycle Time
WIP = Throughput x Cycle Time
Cycle Time = WIP x Throughput
No relationship
4th QUESTION: How can Cycle Time be reduced if Throughput is constant?
Increasing WIP
Working more hours
Reducing WIP
Hiring more people
QUESTION 5: What helps to identify the time measurement in each state?
Team happiness
Lunch time
The budget
Bottlenecks
6th QUESTION: What strategy helps to eliminate bottlenecks?
Ignore them
Increasing WIP
Stop working
Collaboration and automation
7th QUESTION: In what type of system are these metrics especially relevant?
In pure Scrum
In Waterfall
In flow-based systems (Kanban)
In traditional management
8th QUESTION: What is the purpose of managing these metrics?
Optimize flow efficiency
Increase bureaucracy
Reduce quality
Confusing the team
Send